SHCS Calculator
SHCS Calculator
Please fill in ALL the placeholder numbers (in Bold) and read the result (in the BLUE Italized CELLS)
First calculatevolume of air in the greenhouse - fill in the figures in the Greenhouse Dimensions Yellow section
Then fill in the fan, tubing & cost data in the green cellsYour Calculated figures are in italicsData Entry Points are in bold, change any or all.Don't change the italized formula cells!!!Ideal Design Numbers should be: 5 air exchanges per hour and 2-4 feet per sec air speed in the air circulation tubing
Your important Calculated figures are in cells this color
DIRECT YOUR QUESTIONS TO THE SHCS FORUM
STEP ONE Greenhouse Dimensions
STEP ONE Greenhouse Dimensions
Enter a zero in cells that do not apply! BTW, a half circle hoop house has an 180 degree included arc
Box Sections
Box Sections
HeightLengthWidthBox Section Sub total CUFT
Box Section Sub total CUFT
Hoop SectionsArc IncludedRadiusLengthHoop Section Sub Total CUFT
Main4100208000Main
Section2Section2
Section3=b9*c9*d9
0
Section3
Total Square footage2000Design should be 1.33 feet of tubing per square foot2660Get more precise figures for your Hoop Section Volumes from here. Remember to zero out or clear the contents of calculator cells above if you use that other calculator - use the figure you get in the next cell over (just above the calculated value for "Total Hoop Volume CU/ft" which should be blank before you add the figure from the other calculator)8551.2
Total GH Air Volume16551.2Total Box Section CUFT8000Total Hoop Section CU/FT8551.2
STEP TWO FansNB: From the calculated CFM, choose the CFM for the fan you have in mind and enter it (for 0.02" back pressure if you that figure from the manufacturer's data sheet)
Number of FansExchange Rate TIMES/HOUR DesignFan CFM CalculatedFan CFM from Manufacturer ListExchange Rate TIMES/HOUR Calculated
25689.63333333333335003.6251147953018514
Underground Air Circulation Tubing
Underground Air Circulation Tubing
Total Feet of TubingTubing Air Speed FT/SECTime in each Tube SEC
PlenumsTubing DiameterEffective DiameterAverage Length of tubing# of tubes in each plenumTotal Tubing Effective Area SQFT29704.02610678619171213.660839843749999
243.7555274.1396484375
Cost of system hardware
Tubing @ $0.30 per footFans, Plenums, @ approx, $200 per PlenumControls PackageTotal Hardware Costs
$840.00
$891.00
$400.00
$400.00
100
$100.00
1340
$1,391.00
Payback Calculations
Mass of heatsink in pounds480000Heat stored with a 1 F deg rise in heat sink temp480000Your Therm cost ($ per 100,000 BTU's) go herefor rates1.55
$1.55
Stored heat value as natural gas cost per 1 F deg rise
$7.07
$7.44
Expected # of days you get a 1 F deg Rise150
Gas Value gained each year636.12
$1,116.00
Your Electricity Cost in $/kilowatt hour (rates here)0.08
$0.08
Operating cost - fans @ 2 amps for 8 hrs/day
$53.73
$53.73
Yearly Net367.47999999999996
$1,062.27
Hardware Payback in Years1.3094574647547899
 
Average Rating:  Not rated (Not yet rated)
 
Name:  Dean - Copy of SHCS Calculations by  mrhobbit mrhobbit 
Description:  20x100 with 4' walls and 10' high peak, 2 plenums.